Virtus Consult were requested by Simons Group to provide an independent review and delay analysis of the current programme at Sheffield Children’s Hospital. The brief for the delay analysis was to assess the impact on the Accepted Programme, and any required change to the Completion Date, for the compensation event instructing the installation of Cat 6 IT cabling. Also required was a detailed narrative and cause & effect programme [or other appropriate delay demonstration analysis] to demonstrate any assessed delay.